Report By Roger
-------------------------
2 flooring workers time 700 to 330 installing
sanded grout & kimic on the hall way
2 electric workers
GBR crew:
Arturo
Gino
Eleana
Zuli
Rigo
Roger
Oscar warehouse
Installing
Putt drywall on the wall & mug
4 box install
make box on top of the house
(Fireplace Mock up)
----------------------------
Report By Eleana:
----------------------------
a.
Vladimir provided us the chimney mock-up diagram this morning. The
drawing is based on Marvin’s proposal to the HOA on the last meeting where we
angle the vent and move the chimney location directly 5’ back. Jesse/Roger
finished 1 mock-up on the roof today, the other will be completed by tomorrow
(the mock-ups are required by the HOA).
b. Site meeting at 10am tomorrow with
Vladimir, air duct subcontractor, G and me regarding chimney cost, location, and
mock-up. 1st Century Builders is already pricing this based on the
drawing because he could not make it onsite tomorrow.
c. Spoke to Michelle and Vladimir and
extended our deadline from Tuesday 2/2/10 to this
Thursday or Friday to turn in all drawings we are presenting at the next HOA
meeting. We will be presenting:
- Balcony dwgs
- Stone dwgs
- Chimney dwgs
- Guesthouse plans ONLY IF you
approve 100% (Zuli will send to you soon)
d.
Signature acknowledgement for the letter is required by HOA. Per
Michelle, I can go ahead and sign for you since you are gone,
but she will also need an email from you confirming that
you received it. I will sign and fax to her tomorrow.
e. Michelle is informed that Marvin Fong
will not be presenting for us and that we are working on the guesthouse in
house.
Last Friday Flash Electric finished work on the Wok, and began on the Master 1B Dressing. He proceeded work today and was also working on the Kitchen.
Oscar was at the warehouse today, while Jesse/Roger was working on the chimney mock-up.
Gonzalo and helper worked on the single slab in the Kitchen and 1st floor.